Location
Plenty Road, South Morang
Duration
March 2018 – June 2021
Collective
Decmil (contracted by MRPV)
Services
SPH supplied for day and night shifts:
With a $178 Million Dollar Total Project Cost, the Plenty Road Upgrade commenced in March 2018 and was completed in June 2021.
Decmil was awarded the Design and Construct contract for the Plenty Road Duplication between McKimmies Road and Bush Boulevard, Mill Park.
During Stage 1 of the upgrade, the scope of works included an additional new lane in each direction between McKimmies Road and Bush Boulevard, upgrade of five intersections, including Childs Road and Centenary Drive. Traffic lights were installed at Rivergum and Mayfields Drives, the existing footpath was widened and a new shared walking and cycle path was constructed. Built on-road cyclist lanes were installed and 10,000 metres of safety barriers were installed.
An average of 35,000 people use Plenty Road between Bush Boulevard and Bridge Inn Road each day. The Plenty Road Upgrade will provide a safer and more efficient route for Melbourne’s rapidly growing northern suburbs.
Decmil was awarded this contract for the design and construction for Stage 2 of the Plenty Road Upgrade Project which targets the seven kilometre stretch of road between Bush Boulevard and Bridge Inn Road.
The second stage involved upgrading the section between Bush Boulevard in Mill Park to Bridge Inn Road in Mernda. It included: